Interim Management (Change Order Management, Change Management, Claim Management)
Pharmaceutical company
Tracking changes, change orders, and claims in a CAPEX project > €200M
Recording, tracking, and documenting change requests and change orders
Supporting the client in defending against contractor claims
Continuously reducing the impact of changes and change orders on cost and schedule
By preparing a mediation with a law firm, a claim (approx. €1.2M dispute value) was resolved early, ensuring project continuation
Feb 2023 - Dec 2024
1 year 11 months
Germany
Head of Project Procurement (Interim)
Pharmaceutical company
Took over the position of Head of Project Procurement on an interim basis to ensure the timely award of main trades for the construction of a new pharmaceutical production facility
Drafted and negotiated all procurement contracts
Structured preparation of purchasing documents (contracts, negotiation protocols, specifications, etc.) and handed them over to operational procurement
Created management reports for senior management
All trades were negotiated and awarded on time
A seamless handover of responsibilities to a permanent colleague was ensured
Jun 2021 - Sep 2023
2 years 4 months
Germany
Interim Management (Project Procurement)
MDAX company
Independently managed tenders and contract negotiations for individual projects > €100M of the client in construction, engineering services, machinery, equipment, and installation services
Defined the procurement strategy and steered the tender process according to project and procurement plans
Drafted and negotiated procurement contracts in German and English
Structured preparation of contract documents, negotiation protocols, and specifications to ensure proper (SAP) order placement by the client's operational procurement
Prepared management reports
Thanks to PMP expertise, the procurement processes for greenfield and brownfield projects were successfully optimized
A standout achievement was the efficient supplier management for a shutdown project, where an entire production unit was maintained, modified, and partially rebuilt within two months for around €100M
Oct 2019 - Feb 2021
1 year 5 months
Vienna, Austria
Interim Management (Change Management, Change Order Management, Claim Management)
Boehringer Ingelheim
Tracking change requests, change orders, and claims in a CAPEX project > €100M, strictly adhering to the schedule
Due to the COVID-19 situation, an extension of the interim management mandate was required
Weekly site visits to the main supplier, documenting progress, and ensuring timely corrective actions for deviations ensured project success under the changed conditions
Recording, tracking, and documenting all change requests (CRs) in the project
Evaluating and reviewing all change requests (CRs) for their impact on cost, schedule, and scope
Facilitating the weekly CR meeting with the responsible parties from both contractor and client sides
Supporting the client in enforcing or defending against contractor claims
Preparing the weekly CR report for the steering board
Performance monitoring (including documentation and management report preparation) at the main supplier’s site, in compliance with the prevailing COVID-19 regulations
By getting involved early as change and claim manager, I was able to reduce the number of CRs and claims as well as their impact on schedule and cost despite the COVID-19 events
A project audit by a renowned consulting firm raised no findings in change request and claim management
Oct 2018 - Jun 2019
9 months
Vienna, Austria
Interim Management (Contract Management)
team Communication Technology Management GmbH
Stark-Consulting e.U. was a subcontractor to team
A project initiated in April 2015 to switch to smart meters was to be implemented successfully during the acceptance and rollout phases (nationwide installation of about one million meters) in close cooperation with the client's technical project managers and the two main suppliers
Proactively supported project leadership in contract management
Supported the claim and change order process in the project
Assisted the client in enforcing or defending against contractor claims
Necessary adjustment and revision of contracts with the main suppliers for the smart meter rollout
The contracts with the two main contractors were successfully adapted to the requirements for the nationwide installation of smart meters
May 2018 - Dec 2018
8 months
Interim Management (Project Procurement, Change Order Management)
Shire PLC (Baxter AG)
Project procurement for projects focused on equipment, technical building services (TBS) and laboratory equipment
Independently managed international tenders using ARIBA
Drafting and negotiating procurement contracts (in German and English)
Structured preparation of order documents (contracts, negotiation minutes, specifications, etc.) for operational procurement
Change order management
Reporting of achieved savings
Optimizing the procurement process for capital investment projects (CAPEX projects) and supporting the standardization of procurement contracts.
Jun 2015 - Mar 2018
2 years 10 months
Germany
Interim Management (Project Procurement, Change Order Management, Claim Management)
Nestlé Deutschland AG
Project procurement for multiple individual projects over EUR 2 million at various sites, covering machinery, systems, technical building services (TBS) and engineering services
Independently managed international tenders in the areas of machinery, systems, TBS and engineering services
Drafting and negotiating procurement contracts (in German and English)
Structured preparation of order documents (contracts, negotiation minutes, specifications, etc.) to ensure proper (SAP) ordering by operational procurement
Supplier management
Change order management
Claim management
Reporting of relevant procurement KPIs
By involving me early as the project buyer in CAPEX projects, we achieved a significant improvement in the quality of requirements specifications and scope of work documents.
This led to both shorter tendering times and monetary savings averaging 8.5%.
Jan 2015 - Mar 2015
3 months
Germany
Consulting (Contract Management)
Ernst & Young GmbH
Preparing existing contracts for SAP Source-to-Contract management for electronic archiving and scheduling of procurement contracts
Creating a contract overview and aligning with stakeholders in procurement and specialist departments
The contract overview was created and prepared for import into the Source-to-Contract system.
Sep 2014 - Jan 2015
5 months
Hamburg, Germany
Consulting (Procurement Process Optimization)
Otto (GmbH & Co KG)
Analyzing, evaluating and optimizing the tendering process in the area of 'non-trade goods procurement' and developing a proposal for a target concept
Recording and analyzing the current tendering process
Optimizing and developing a target-state tendering process for implementation on the group's eSourcing platform (IBX)
Independently conducting live demos on the IBX eSourcing platform
Creating a comprehensive report including an action plan for implementing the target concept
Documenting the processes in BPMN 2.0
Developing a commodity group concept proposal including an action plan for supplier consolidation
The weaknesses of the current tendering process were thoroughly analyzed and replaced with a target concept tailored to the IBX eSourcing platform
This led to shorter tendering times and improved quality of bids submitted by suppliers on the eSourcing platform.
Dec 2013 - May 2014
6 months
Vienna, Austria
Consulting (Project Management, PMO)
Baxter AG
Implementing Oracle Primavera Unifier as the system for procurement and project controlling of global investment projects
Creating a process overview according to PMI standards for the Project Management Office (PMO)
Describing and modeling business processes in the ADONIS process management system and mapping them in Primavera Unifier
Independently conducting system tests and documenting the results
Creating error reports and developing improvement suggestions
Participating in process team meetings in the USA
Successfully adapting and implementing the process guidelines from the group headquarters in the USA to local conditions.
Jun 2013 - Oct 2013
5 months
Bonn, Germany
Consulting (Project Procurement)
Deutsche Telekom AG
Assisted in preparing tender documents (in English) and evaluating submitted bids for a Machine to Machine (M2M) middleware project.
Supported the development of the M2M business model and documented the processes
Evaluated the bids and prepared data for the management summary
Thoroughly analyzed the vendors' bids and integrated them into the M2M business model
Developed extensive scenarios for this investment project and prepared them for the steering board.
Dec 2012 - Jun 2013
7 months
Halle, Germany
Head of Technical Procurement (Interim)
Baxter Oncology GmbH
Managed all procurement activities for a €58M investment project in the pharma sector.
Led a procurement team of two (2) employees
Developed the procurement strategy and oversaw the entire procurement process for this investment project
Negotiated contracts and supported the legal department in drafting purchase agreements
Defined and successfully implemented the procurement process for this investment project
Achieved a 12% cost saving while simultaneously improving supplier services.
Managed global projects in the categories of construction, production equipment (machinery and supplies), facility management, and utilities as part of a global program aimed at cost savings and efficiency improvements
All project communication was conducted exclusively in English
Defined relevant KPIs for continuous monitoring of the performance of individual subsidiaries
Project controlling
Supplier consolidation
Provided expertise to identify, implement, and continuously improve best practices, systems, and processes
Achieved and even exceeded the set savings target in the mid-double-digit millions USD range.
Advised the technical and procurement departments on tenders for leasing colocation spaces in the telecommunications sector
Advised on preparing tender documents (in German and English)
Evaluated the submitted bids
Developed negotiation strategies
Supported the client in contract negotiations
Successfully negotiated and concluded contracts with five (5) colocation providers.
Sep 2010 - Apr 2011
8 months
Bonn, Germany
Interim Management (Strategic Procurement)
Deutsche Telekom AG
Developing procurement strategies and optimizing procurement processes to achieve sustainable cost savings for rollout projects
Analyzing and preparing existing data (SAP and data warehouse) from the client
Converting existing contracts into new procurement models
Modeling procurement processes for rollout projects
Defining processes for implementation in SAP MM/SRM
Analyzing data from completed rollout projects and optimizing order processes for upcoming 4G projects
Aug 2010 - Nov 2010
4 months
Graz, Austria
Consulting (Strategic Procurement)
smaXtec animal care Sales GmbH
Advising on building a service partner network in Germany, the Netherlands, and France
Evaluating and selecting mobile network operators for connecting devices to machine-to-machine (M2M) GSM/UMTS networks
Identifying suitable service partners and successfully concluding the corresponding framework agreements
Nov 2009 - Mar 2010
5 months
Germany
Consulting (Tender Management)
Client in Germany
Advising in bid management and developing the sales strategy
Managing the bidding process
Supporting the development of a sales strategy
The client won the contract and became a supplier to an international company
Sep 2009 - Dec 2009
4 months
Schladming, Austria
Consulting (Project Management)
Planai-Hochwurzen-Bahnen GmbH
Advising accommodation providers on integrating a local TV station
Concluding framework agreements with cable network providers and TV/SAT installation companies
Estimating investment costs for individual accommodation providers
Managing the technical implementation
Within three months, advised 200 accommodation providers across the broadcast area on the required investments in TV/SAT systems for receiving Planai-TV
Concluded framework agreements with leading TV/SAT equipment manufacturers, cable network providers, and installation companies
Jul 2009 - Sep 2009
3 months
Feldkirchen in Kärnten, Austria
Consulting (Project Procurement)
Balent Baumaschinen
Advising on the procurement of a dredger
Conducting a risk assessment for the procurement process
Preparing a detailed risk assessment as the basis for negotiations with the client's and the supplier's house banks
Mar 2009 - Apr 2009
2 months
Vienna, Austria
Consulting (Procurement, Tender Management)
sync inc Design Build GmbH
Preparation of tender documents for hardware, software, and network infrastructure of an architecture firm.
Preparation of the bill of quantities and tender documents.
Within two (2) months, the entire IT network infrastructure was tendered, negotiated, and installed.
Summary
Expert in project procurement, contract, change, and claim management for projects > €10M
International mandates with large corporations (pharmaceutical, food, telecommunications, raw materials, energy utilities, mail order, consulting)
Project manager for implementing investment (CAPEX) projects > €10M
Specialist in analyzing and optimizing business processes for procurement and project management (PMO)
Expert in executing projects in Six Sigma (Black Belt level) and Lean Management
Process-oriented executor with a clear focus and strong quality awareness
Ability to analyze, prepare, and present complex issues
High interdisciplinary technical, commercial, and contract law expertise
Successful negotiation track record at the international level
Languages
German
Native
English
Advanced
Education
Oct 1985 - Jun 1994
Graz University of Technology
Diploma Engineer, Electronics and Communications Engineering · Electrical Engineering · Graz, Austria
Oct 1979 - Jun 1984
Higher Technical Federal Institute for Electrical Engineering
Matura (High School Diploma) · Electrical Engineering · Kapfenberg, Austria