Experience

Aug 2024 - May 2025
10 months
Leipzig, Germany

Freelance Operations Engineer

Stadtwerke Leipzig HKW Süd

Feb 2023 - Present
2 years 7 months
Hybrid

Project Manager

BS Energy Braunschweig

Project management of

  • Boiler plants
  • Electrical engineering
  • Process control systems
Feb 2023 - May 2025
2 years 4 months
Braunschweig, Germany

Project and commissioning lead for peak load boilers, freelance external employee

BS/Energy

Jul 2022 - Feb 2023
8 months
Frankfurt, Germany

Project manager/subproject manager for process, electrical and DCS engineering, power plant and district heating projects,

Mainova AG

Jan 2020 - Jun 2022
2 years 6 months
Vohburg an der Donau, Germany

Specialist construction and commissioning lead for mechanical, electrical and control engineering in Irsching Block 6 new-build

Uniper System Stabilität GmbH

Jan 2017 - Dec 2020
4 years
Berlin, Germany

Project Manager and Instructor for Power Plant Technology

Modis GmbH

  • Power plant technology department
  • Burner conversion project of a 1000 t/h steam generator at HKW Reuter West for Vattenfall Wärme Berlin
  • Power-to-Heat plant project for Wärme Hamburg
  • Replacement of a boiler feed pump at Huber-Werke Bergheim
  • Investigation of a KKK drive turbine after overhaul (water in oil)
  • Technical project specialist for the CCGT plant at Ineos Cologne, gas and steam turbine
  • Technical manager of the biodiesel plant in Niederpöllnitz
  • Expansion of the esterification plant
  • New construction of a thin-film evaporator plant
  • Migration of the PLS from Automation X to PCS 7
  • Commissioning and management of the new plant
Jan 2016 - Dec 2016
1 year
Wedel, Germany

Project Manager

Vattenfall Wedel

  • Overhaul of main power plant units
  • Execution of overhauls
  • Construction site management
  • Preparation of overhaul documentation
  • Personnel management
Jan 2014 - Dec 2017
4 years

Self-employed Project Manager and Instructor

  • Project management for new construction, overhaul, commissioning, and decommissioning of power plant systems
  • Conducting turbine and boiler diagnostics, fault analysis
  • Performing turbine endoscopies and preparing reports
  • Optimization of boiler and combustion systems
  • Preparation and execution of overhauls
  • Optimization of FLR (combustion performance control)
Jan 2014 - Dec 2016
3 years
Flensburg, Germany

Project and Commissioning Manager

Stadtwerke Flensburg

  • New installation of a 30 MWh steam turbine within an existing building envelope as part of a CCGT plant
  • Delivery and installation of the steam turbine with auxiliary systems
  • Complete piping installation
  • Electrical and control engineering
  • Commissioning and trial operation
  • Management of installation personnel
  • Client relations
Jan 2014 - Dec 2015
2 years

Instructor

TÜV Nord Akademie

  • Boiler operator training
  • Steam and pressure technology
  • Occupational health and safety
  • Instruction of electrical personnel according to VDE/VDI
  • Turbine construction/commissioning
Jan 2009 - Dec 2014
6 years
Rostock, Germany

Head of Production/Maintenance

Vattenfall Europe New Energie Ecopower

  • EBS-HKW Rostock
  • Managing the production process
  • Achieving high plant availability
  • Leading staff (production and maintenance)
  • Ongoing plant optimization
  • Monitoring and controlling resources
  • Planning and directing overhauls and shutdowns
  • Ensuring compliance with regulatory requirements and permits
  • Conducting turbine overhaul (Siemens SST 300)
Jan 2009 - Dec 2009
1 year

Project Manager

Fa. Weiss, Kessel- Maschinen -und Anlagenbau

  • Project preparations
  • Work preparation
  • Procurement specifications
  • Organizing and leading kick-off events
  • Contract negotiations
  • Commissioning of boiler plants (E- and LT)
  • Technical and schedule planning
  • Acceptance tests
  • Cost monitoring / financial statements
  • Commissioning of boiler plants
  • Optimization of CHP plants (combustion, turbine performance, emission limits)
Jan 2005 - Dec 2009
5 years
Schkölen, Germany

Operations Manager/Power Plant Manager

Biomasseheizkraftwerk Schkölen

  • New construction of the plant within an existing building shell
  • Expansion into a CHP plant with a DT MARC 2 C 45
  • Taking over the plant as Operations Manager
  • Managing the production process
  • Leading staff
  • Monitoring and controlling resources
  • Ensuring compliance with regulatory requirements and permits.
Jan 2004 - Dec 2005
2 years
Cologne, Germany

Consortium Project Manager EBS Systems

WTW Engineering GmbH

  • EBS additional injection at RWE Power Werne
  • Leading the bidder consortium (ABB, WTW, Wiemer &Trachte)
  • Contract negotiations with contractors and clients
  • Technical and schedule planning
  • Commissioning of the EBS system
Jan 1995 - Dec 2005
11 years
Neubrandenburg, Germany

Project Manager/Senior Construction Manager

Strabag AG

  • Contract negotiations
  • Preparation of contract addenda and defending them before the client
  • Technical and schedule planning
  • Project costing
  • Highway construction, federal roads, port construction projects
  • Acceptance tests
  • Liaising with authorities, permitting processes
  • Cost control / financial statements
  • Personnel and
Jan 1985 - Dec 1995
11 years
Bitterfeld-Wolfen, Germany

Operations Engineer, Plant Manager, Project Manager for Power Plant Reconstruction

BKK Bitterfeld/Mibrag Bitterfeld

  • Negotiating contracts with subcontractors
  • Technical and scheduling development planning
  • Reconstruction of the boiler systems at the Mumsdorf power plant
  • Construction of district heating systems including converter stations
  • Creating schedules
  • Acceptance inspections
  • Cost monitoring and balances
  • Personnel and budget planning
  • Coordination with independent inspection bodies (ZÜS) and authorities
Jan 1969 - Dec 1984
16 years
Neukieritzsch, Germany

Chief Operator, Shift Supervisor

Kraftwerk Lippendorf

  • Operating the 4 x 100 MW units
  • Starting up and shutting down the units
  • Personnel scheduling (shifts)
  • Cost control of operating resources
  • Reducing auxiliary consumption and fuel costs

Summary

Work Experience: I have been working in power plants for 55 years (see also CV), 30 years on the operator side and 25 years on the construction side.

  • Combined cycle plants
  • Gas turbine plants
  • Boiler plants
  • Steam turbines
  • Thermal storage

Languages

German
Native

Education

Oct 1984 - Jun 1989

Technische Hochschule Leipzig

Dipl.-Ing. (FH) · Energy Technology, Power Plant Technology · Leipzig, Germany

Oct 1966 - Jun 1969

Kraftwerke Lübbenau/Vetschau

Thermal power plant operator, high school diploma · Vetschau, Germany

Sep 1956 - Jul 1966

Oberschule Treben

10th grade school leaving certificate · Treben, Germany

Certifications & licenses

Periodic test for switching authorization up to 30 kV

TÜV Süd

Periodic test for switching authorization up to 30 kV

TÜV Nord

Periodic test for switching authorization up to 30 kV

TÜV Süd

Master craftsman in general mechanical engineering

Switching authorization up to 110 kV

Need a freelancer? Find your match in seconds.